Feasibility
Stage duration: 1 month
We undertake initial surveys to define the solar farm site boundary within available lands.
This feasibility stage also assesses substation and grid connection requirements, landscape and environmental aspects and the needs of adjacent and future landowners.
Lease and Ownership
Stage duration: 2 months
We work with the landowner to take an option for lease on the solar farm lands, which allows us to progress planning and grid connection consents.
Terra Solar will cover the cost of landowners’ legal advice for the lease option process.
Grid Connection and Planning Permission
Stage duration: 12 months
Once the option for lease is signed, Terra Solar will finalise design work and apply for planning permission both the solar farm and grid connection, liaising with local government and communities and considering the natural environment.
During this period, the landowner can continue to use the lands as before.
Development
Stage duration: 24 months
The lease of the solar farm lands commences once construction begins.
On completion, the solar farm is operational and generates renewable electricity which is fed into the National Grid.